Projects

Pacific Highway Upgrade – Kundabung to Kempsey

RoadNet Projects1Project Dates
2014 – 2017

Client
McConnell Dowell York Civil Joint Venture

Principal
RMS

Project Value
$230 million

Project Length
14 km

Project Description
Upgrade of approximately 14 kilometres of the Pacific Highway to a four lane divided road between Barrys Creek in Kundabung and the South Kempsey Interchange.

This project involved building an interchange at Kundabung Road, new intersections for local access roads, bus stops and new rest areas.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Consulting with construction contractor to develop construction staging methodology;
  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic Control Plans;
  • Undertaking of civil design of temporary sidetracks and intersections;
  • Undertaking temporary drainage design and analysis;
  • Undertaking design of signage;
  • Undertaking dilapidation surveys;
  • Undertaking road safety audits.

For more information on this project refer to RMS website:
http://www.rms.nsw.gov.au/projects/northern-nsw/oxley-highway-to-kempsey/kundabung-to-kempsey.html

Pacific Highway Upgrade – Warrell Creek to Nambucca Heads

RoadNet Projects2Project Dates
2014 – 2018

Client
Acciona Ferrovial Joint Venture

Principal
RMS

Project Value
$820 million

Project Length
20 km

Upgrade of approximately 20 kilometres of the Pacific Highway to a four lane divided road between Warrell Creek and the Nambucca Heads.

This project involved building 15 bridges, interchanges at Warrell Creek and Bald Hill Road and new intersections for local access roads.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Consulting with construction contractor to develop construction staging methodology;
  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic Control Plans;
  • Undertaking of civil design of temporary sidetracks and intersections;
  • Undertaking temporary drainage design and analysis;
  • Undertaking design and certification of temporary pavements;

For more information on this project refer to RMS website:
http://www.rms.nsw.gov.au/projects/northern-nsw/warrell-creek-to-nambucca-heads/index.html

Warrego Highway / Brisbane Valley Highway – Blacksoil Interchange

RoadNet Projects3Project Dates
2013 – 2015

Client
Fulton Hogan

Principal
TMR

Project Value
$94 million

Project Length
2 km

This project involved the grade separation of Warrego Highway and Brisbane Valley Highway at Blacksoil, west of Ipswich. The key benefits of the upgrade were to improve safety and increase capacity of the intersection to meet the transport needs of the region well into the future.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Consulting with construction contractor to develop construction staging methodology;
  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic guidance Schemes;
  • Undertaking civil design of temporary sidetracks and temporary intersections;
  • Undertaking temporary drainage design and analysis;
  • Undertaking temporary pavement design and certification;
  • Undertaking temporary lighting design;
  • Undertaking temporary traffic signal design;
  • Undertaking signage designs;
  • Undertaking road safety audits;
  • Undertaking AIMSUN and SIDRA traffic modelling;

Gold Coast Light Rail – Stage 2

RoadNet Projects4Project Dates
2016 – 2017

Client
CPB Contractors

Principal
TMR

Project Value
$420 million

Project Length
7 km

This project involved the Stage 2 7 kilometre extension of the Gold Coast light rail from the University Station to the Helensvale Train Station.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Consulting with construction contractor to develop construction staging methodology;
  • Preparing Traffic Staging Plans;
  • Preparing Traffic Guidance Schemes.

Pacific Highway Upgrade – Woolgoolga to Halfway Creek

RoadNet Projects5Project Dates
2015 – 2017

Client
OHL York Civil Joint Venture

Principal
RMS

Project Value
$200 million (estimate)

Project Length
14 km

This project involved the upgrade of approximately 14 kilometres of the Pacific Highway to a four lane divided road between Arrawarra interchange and Grays Road at Halfway Creek., including building an interchange at Kundabung Road, new intersections for local access roads, bus stops and new rest areas.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Consulting with construction contractor to develop construction staging methodology;
  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic Control Plans;
  • Undertaking of civil design of temporary sidetracks and intersections;
  • Undertaking temporary drainage design and analysis;
  • Undertaking design and certification of temporary pavements;
  • Undertaking analysis of ultimate pavement and development of alternative designs;
  • Undertaking culvert construction loading analysis and certification.

For more information on this project refer to RMS website:
http://www.rms.nsw.gov.au/projects/northern-nsw/woolgoolga-to-ballina/woolgoolga-to-halfway-creek.html

Pacific Motorway Upgrade – Nerang to Worongary

RoadNet Projects6Project Dates
2010 – 2013

Client
Fulton Hogan

Principal
TMR

Project Value
$420 million

Project Length
5 km

This project involved the upgrade of approximately 5 kilometres of the Pacific Motorway from four lanes to six lanes between Nerang and Worongary to help improve the congestion of traffic during peak hours.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Consulting with construction contractor to develop construction staging methodology;
  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic Control Plans;
  • Undertaking of civil design of temporary sidetracks and intersections;
  • Undertaking temporary drainage design and analysis;

New England Highway / Crystalbrook Road upgrade, Guyra NSW

RoadNet Projects7Project Dates
2014 – 2015

Client
Costa Group

Principal
RMS

Project Value
$5 million

Project Length
1 km

This project involved the upgrade of the intersection with the New England Highway and the tomato farm access road, design and construction of the internal tomato farm access road and the upgrade of the New England Highway and Crystalbrook Road intersection just north of Guyra, NSW.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Preparing Traffic Impact Assessment for Tomato Farm development;
  • Undertaking civil design of the concept and detailed design of intersections and internal access road;
  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic Control Plans;
  • Preparing Works Authorisation Deed (WAD);
  • Undertaking permanent and temporary pavement designs;
  • Undertaking desktop road safety audits.

Great Western Highway – Hartley Valley to Forty Bends

RoadNet Projects8Project Dates
2014 – 2017

Client
Seymour Whyte Constructions

Principal
RMS

Project Value
$133 million

Project Length
12 km

This project involved the upgrade of about 12 kilometres of highway between Hartley Valley and Forty Bends west of Sydney including improvements to existing geometry, curves and road surface, reduction in the risk of black ice formation and the upgrade of five main intersections.

RoadNet was the temporary works design consultant for this project undertaking tasks including:

  • Preparing Traffic Staging Plans;
  • Preparing long term Traffic Control Plans;
  • Undertaking civil designs for temporary sidetracks and temporary road widening.

For more information on this project refer to RMS website